VSR Infrastructure Pvt Ltd: Just think about that you’ve invested all of your financial savings in shopping for a house and now you’re neither getting the house nor the cash from the builder. Something related occurred with Nirmal Satwant Singh of Gurugram. On July 24, 2013, he booked three flats in 114 Avenue from Delhi-based builder VSR Infrastructure Private Limited. Nirmal paid Rs 2.4 crore for these three flats. The builder promised him the possession inside three years, however quickly 11 years handed however Nirmal didn’t get the possession of the flat from the builder.
Builder refused to give refund
Nirmal tried to resolve this problem by speaking to the company a number of instances, however the builder stored hedging each time. Nirmal appealed to the company to both give him the possession of the flat or give him a refund, however the builder neither gave him the possession and later even refused to give the refund. Ultimately Nirmal approached the Consumer Commission for assist.
The company offered its facet in the court
Arguing in opposition to this motion of Nirmal, VSR Infrastructure Private Limited mentioned that the individual shopping for the house is just not a client, therefore resolving his problem doesn’t come underneath the purview of the Consumer Court. Along with this, the company demanded the court to reject Nirmal’s petition. The company additionally instructed the court that Nirmal had purchased the house for his personal profit and never for industrial functions.
While presenting its stand, the company additionally mentioned that the delay in possession is due to air pollution and the ban on building imposed by the authorities. The company mentioned that the flat is prepared, solely the occupancy certificates is but to be acquired, the possession will probably be given as quickly as it’s acquired.
Court reprimanded the builder
Here, the court reprimanded VSR Infrastructure Private Limited and rejected all their arguments. The court mentioned, the individual shopping for a house additionally is available in the class of client. The house could have been purchased for dwelling in, however cash has been paid for it.
Along with this, the court ordered the company to refund Rs 2.4 crore to Nirmal. Apart from this, directions had been additionally given to give Rs 5 lakh for psychological harassment and Rs 50,000 as compensation for the bills incurred in the authorized battle.